A project is a temporary endeavour undertaken to provide a unique service or result.

Scope

Triple Constraint

The triple constraint demonstrates the three axes of critical project focus in regards to deliverables.

It states that changes in one constraint must mean compensation in others. As such, the PM may trade focus between constraints.

Typically, all three constraints are unattainable for a single project: “Good, fast, cheap. Choose two.”

Work Breakdown Structure (WBS)

A project should be broken down into components, which is further broken down into work packages (WP)

A work package should have minimal horizontal interaction. As such, they should group tasks into relevant chunks. They should be easy to parallelise.

  • Smaller WPs are more estimable and measurable, but harder to define - risking horizontal overlap.
  • Larger WPs are easier to manage and are typically more efficient but risks the PM having less control and may overrun.

Critical Path Method (CPM)

We can draw a Project Network Diagram which shows dependencies between tasks within a project. This can be extended to find the critical path in a network - this will allow us to detect bottlenecks.

We describe an algorithm to generate the critical path network:

  • Start with a PND. We note every activity has 6 parts.
  • We begin the forward pass. Starting with the start activity and continuing to the end, we find:
  • Then, we complete the backward pass. Startting with the end activity and continuing to the start, we find:
  • Finally, we may find the slack with .
  • We may find the drag with .

Budgeting & Forecasting

The process of budgeting is creating a cost estimate. This is split into sections.

Cost Management

Initially, estimating a cost involves accounting for overspend and uncertainty. This creates the need for reserve funds in an estimate - contingency funds.

Activity Management

This is the need for a cost estimate for a given activity. This may be, for example, cost per hour, for human resource allocation.

AM may also include estimation curves, as used with the PERT method for time management. Breaking a project down (using a WBS) makes it easier to estimate activity costs.

Earned Value Analysis

We can use several values to keep track of a project’s cost status. We note:

  • PV = Budget at time
  • AC = Cost,
  • EV = Taking a look at the lines above, we can draw some conclusions:

The gap between EV and AC () is the cost variance, defined as the magnitude of budget deficit or surplus.

  • implies the project is under budget.

The gap between EV and PV () is the schedule variance, defined as how delayed or ahead of schedule the project is.

  • implies the project is ahead of schedule.

In terms of a graph, an ideal scenario is where and .

To further this, SPI, CPI and CSI can be introduced.

SPI is a ratio measure of how on-schedule () a project is. CPI is a ratio measure of how at-budget () a project is. As such, CSI is a measure of overall efficiency.

Forecasting

This can also be done with Earned Value Analysis.

There are several forecasting methods:

  • Estimate at Completion, (), estimates total cost based on current progress.
  • Estimate to Complete, (), estimates the remaining cost of work.
  • Variance at Completion, (), is the derivation from budget.
  • To-Complete Performance Index is the cost efficiency required to achieve the BAC or EAC, below: TCPI_{BAC} = \frac{BAC - EV}{BAC - AC}$$$$TCPI_{EAC} = \frac{BAC - EV}{EAC - AC}